Case Study

Commissioning of Overhead Cranes for an EAF Furnace

Support for the Commissioning of EAF Overhead Cranes in Linz

Key facts
Project
Greentec Steel – New Electric Arc Furnace (EAF)
Client
Felbermayr Deutschland GmbH
Technical supervision
Felbermayr Deutschland GmbH
Location
Linz, Austria
RAO scope

Construction of an Auxiliary Structure

Environment
Heavy Lift · Rigging · Preparation
TAGS
HEAVY LIFT, RIGGING, ROPE ACCESS
In brief
RAO supported the Felbermayr Deutschland GmbH team during the commissioning of two overhead cranes for the new EAF at the Greentec Steel facility in Linz. Our team assembled the lifting structure, prepared the rigging equipment, positioned components, and dismantled the equipment upon completion of the work. The operation involved a scrap charging crane with a rated lifting capacity of 450 t, load-tested at 565 t during the official AMVO inspection, and a molten metal handling crane with a lifting capacity of 265 t.
Project
Two overhead cranes were installed at the Greentec Steel facility in Linz to support the operation of the new electric arc furnace (EAF). RAO participated in the on-site operation, working alongside the Felbermayr Deutschland GmbH team.

Crane Specifications

Scrap charging crane: rated lifting capacity of 450 t; during the official AMVO inspection, it was load-tested at 565 t.

Molten metal handling crane: lifting capacity of 265 t.
RAO scope of work

Installation of the auxiliary structure used during lifting operations and preparation of rigging equipment for use. RAO riggers positioned and prepared components for lifting and, upon completion of the project, dismantled the equipment used during the operation.

The work was carried out using cranes, Manitou telehandlers, chain hoists, and other rigging equipment.

Execution

The operation required precise equipment preparation, correct positioning of components, and close coordination between multiple teams on site. Given the heavy loads involved, careful planning, clear communication, and strict adherence to the agreed method of work were essential.

Result
The RAO team successfully completed the assigned scope, including the preparation and installation of rigging equipment and its dismantling upon completion of the work. The operation was carried out in close cooperation with the Felbermayr Deutschland GmbH team.
Safety
Safety Score: 100% | Zero Harm / Zero LTI