Case Study
Offshore · System Deluge
Deluge System Maintenance on the Hilli Episeyo
Key facts
Project
Fire Protection System Maintenance
Client
Golar
Technical supervision
Siron
Location
Cameroon
RAO scope
Fire Protection System Cleaning & Testing
Environment
Offshore
TAGS
OFFSHORE, FIRE FIGHTING, ROPE ACCESS, RIGGING
In brief
For over a year, RAO supported Siron with work on the Deluge system aboard the Hilli Episeyo, operating offshore near Kribi, Cameroon. The team supervised rope access operations and carried out work on the piping system, including dismantling, high-pressure internal cleaning, reassembly, and Dry Deluge testing. The work was performed under daily Permits to Work in an offshore environment, including hazardous areas with potentially explosive atmospheres.
Project
For over a year, RAO supported maintenance work on the Deluge fire protection system aboard the Hilli Episeyo, a floating LNG facility operating offshore near Kribi, Cameroon. The work was commissioned by Siron and covered an extensive network of fire protection piping and components in an offshore environment, including hazardous areas with potentially explosive atmospheres.
The work required strict adherence to safety procedures. Each day, the team received a Permit to Work for a clearly defined scope and work area.
The work required strict adherence to safety procedures. Each day, the team received a Permit to Work for a clearly defined scope and work area.
RAO scope of work
RAO supervised rope access operations and carried out work on the piping system, combining rope access, pipefitting, and rigging. The scope included:
- dismantling pipe sections using rope access techniques,
- high-pressure internal cleaning of pipes,
- reassembly of pipe sections,
- testing of system components,
- Dry Deluge system testing.
Execution
The work was carried out in stages under daily Permits to Work defining the approved scope and work location. The RAO team performed each task within the designated area, in accordance with site requirements and the procedures applicable to hazardous areas with potentially explosive atmospheres.
Result
For over a year, the RAO team was involved in testing components of the Deluge system, followed by work on the piping and system testing after reassembly.
Safety
Safety Score: 100% | Zero Harm / Zero LTI