Case Study
Major Component Replacement
Operational Support for the Replacement of Five Generators and One Wind Turbine Blade
Key facts
Project
Major Component Replacement
Client
N/A
Technical supervision
N/A
Location
The Netherlands, North Sea
RAO scope
MCE · Heavy Lift · Offshore · Rigging
Environment
Offshore
TAGS
MCE, OFFSHORE, BLADE, RIGGING
In brief
RAO supported the replacement of five generators and one wind turbine blade at an offshore wind farm, carried out for DWT. We provided experienced riggers to join the team working in the upper section of the turbine. Our specialists were directly involved in component replacement, equipment preparation and positioning, lifting operations, as well as the loading and organisation of equipment on board the vessel.
Project
The project involved the replacement of five generators and one wind turbine blade at an offshore wind farm. The operation required the coordination of rigging activities, preparation and loading of the transport vessel, and organisation of components and equipment prior to the replacement works.
RAO scope of work
RAO provided experienced riggers who joined the team working in the upper section of the turbine. The team was directly involved in component replacement, equipment preparation and positioning, and the execution of lifting operations.
Prior to the start of the replacement works, the team supported project preparation, vessel loading, and the positioning of components and equipment in designated locations. Proper organisation of the cargo and equipment was essential to ensuring the smooth and efficient execution of each subsequent stage of the operation.
Execution
- provision of experienced riggers for the offshore team,
- support for the top tower team,
- involvement in the replacement of five generators,
- involvement in the replacement of one wind turbine blade,
- equipment preparation and positioning,
- support for lifting operations,
- vessel loading,
- positioning of components and equipment,
- support during project preparation.
Result
The RAO team successfully delivered the assigned scope as operational support, with our riggers involved in both logistical preparations and on-site activities supporting the replacement of five generators and one wind turbine blade.
All work was carried out in accordance with project requirements and the safety standards applicable at the offshore site.
All work was carried out in accordance with project requirements and the safety standards applicable at the offshore site.
Safety
Safety Score: 100% | Zero Harm / Zero LTI